fcgov.com logo
fcgov.com print logo
FCGov.com logo holder
image of fort collins

Update May 28th, 2008

Road Closure Alert June 1-July 1, 2008

The roundabout at Horsetooth and Ziegler is almost complete.

Horsetooth Road at Kingsley Drive, to Ziegler Road will be closed to east bound traffic for one month. The road closure will allow crews to finish the remaining section of the roundabout.

Motorist traveling east on Horsetooth please use the alternate route: Timberline south, east on to Harmony.

Traffic traveling north on Ziegler to Horsetooth will travel on the new section of the roundabout and turn west onto Horsetooth.

HZIP March-April 2008

Construction Begins on the Horsetooth-Ziegler Roundabout and Ziegler Road Improvements

Phase II of the Harmony-Ziegler Improvement Project (HZIP) is underway at the intersection of Horsetooth Road and Ziegler Road. A roundabout is being installed at the intersection and a quarter mile stretch of Ziegler Road is being widened.

The entire project will take approximately four months to complete. Initially, lanes will not be closed. Some lane shifts and slower traffic flow should be expected on those sections of Horsetooth and Ziegler. Naranjo Civil Constructors is the contracting firm on the project.

Starting in May, a portion of eastbound Horsetooth Road between Ashmont and Ziegler will be closed to allow for construction of the second phase of the roundabout. Residents and commuters will need to find alternative routes; there will be signs on site for detour routes.

HZIP is a $33 million construction project that Bayer Properties, developers of Front Range Village, has helped fund in anticipation of the lifestyle center’s summer 2008 opening. Phase I of HZIP was completed between July and November 2007.

WHY A ROUNDABOUT?

Bayer Properties and the Front Range Village Development were required to make improvements to the Horsetooth/Ziegler Intersection based on the additional traffic that would be traveling through the intersection as a result of their development.

Based on the unusual pattern of traffic through the intersection where the west and south legs of the intersection see the majority of the traffic, a roundabout was determined to be the best solution to mitigate congestion and improve the intersection for the post-development conditions.

H-ZIP August Update

Ziegler Road, Corbett Road, and Gifford Court Reopen to Traffic along Harmony Road on August 19, 2007

The City’s engineering department is pleased to announce the reopening of all impacted intersections within the HZIP wok boundaries on Aug. 19th. Due to the aggressive schedule, multiple contractors and City departments have been working since late June to widen Harmony and Ziegler. Here’s what to expect after Sunday, August 19th:

  • Ziegler/Harmony Intersection will be reopened. Ziegler Road will be one lane each direction with turn lanes. Harmony Road will be two lanes each direction with turn lanes.
  • Corbett/Harmony Intersection will be reopened.
  • Gifford/Harmony Intersection will be reopened.
  • Curb and gutter work continues on Harmony Rd. and Ziegler Rd.
  • Widening work along Ziegler Road will begin. Widening work along Harmony will continue.
  • Median Landscaping and overhead lighting work will begin

Traffic to and from the local schools in that area will not be restricted by intersection closures. However, the Harmony Ziegler Improvement Project is still under construction. Lanes will drop and move as construction crews complete work on Harmony from west of Snow Mesa to Lady Moon over the next several months. Construction is scheduled to wrap up for the winter in November. Phase II of HZIP will resume in the spring.

Safety and caution are extremely important on this, and all City projects. Please drive carefully. Thank you for your continued patience.

August 3rd-August 19th

  • August 9th traffic along Harmony was switched from the south two lanes, to the north side. This allowed crews to finish the Ziegler/Harmony Intersection and Harmony/Corbett Intersection work. Both east and west bound travelers were given a designated lane. The south side was closed to traffic as new asphalt was applied.
  • Total intersection closures occured at:
    • Harmony/Gifford
    • Harmony/Corbett
    • Harmony/Ziegler.
  • Northbound Ziegler, south of Harmony, was blocked at Rock Creek Drive. Signs directed vehicles to take a detour that goes east on Rock Creek, then north on Lady Moon.
  • Signage was also in place directing traffic to use Snow Mesa for Local Business Access.

H-ZIP July Update

Construction on the Harmony – Ziegler Improvement Project is well underway. Lafarge – North America was awarded the contract in June and promptly began construction on June 25, 2007.

The last week of June and the first week of July, HZIP crews concentrated on installing "shoeflies" and doing other work in preperation for the roaday closure. A “shoefly” is the temporary piece of asphalt that is placed in the median area to allow traffic to detour across an existing median.

HZIP’s partial roadway closure occurred on Monday, July 9, 2007 and went very smoothly. That same day, traffic signals at Ziegler and Corbett were disconnected, asphalt was milled at the Ziegler and Corbett intersections and utility relocations were initiated.

During the third week in July, Schmidt Earth installed pipe systems, Concrete Structures, Inc installed inlet boxes, and Northstar Concrete installed median curb and gutter. All of these processes are in preparation for new landscaped medains along the Harmony Corridor.

During the fourth week of July, Schmidt Earth finished gradeing the intersection for concrete paving operations and Northstar Concrete was right behind them installing the concrete pavement in the Harmony-Ziegler intersection. Concrete intersection placement begins at 5:00 AM every morning and is wrapped up by noon. The concrete finishers then setup the concrete forms and reinforcing steel in the afternoon for the next morning’s pour.

WORK THAT HAS BEEN COMPLETED:

  • Temporary shoe-flies installed in Harmony medians for traffic control.
  • Traffic signal poles and concrete bases were removed. New bases were also re-installed on Harmony-Ziegler.
  • Asphalt concrete milled out on the North half of Harmony Road.
  • Topsoil, grass and trees removed in areas of widened roadway. Three pieces of the large cottonwood trees that were removed along Ziegler were saved by motivated citizens and the City’s Forestry Department for educational purposes.
  • Reinforced concrete pipes and inlets are installed along the Harmony medians.
  • Approximately 50% of HZIP’s planned concrete curb and concrete pavement is already installed.

AUGUST’S CONSTRUCTION SCHEDULE:

  • We will continue installing concrete pavement along Ziegler and Harmony Road.
  • Asphalt paving operations will also be concentrated along the north half of Harmony Road.
  • City of Fort Collins Traffic Dept will install signal poles and new traffic signals at Corbett and Ziegler.
  • Fort Collins Utilities will install overhead lights inside the Harmony road medians.

Work is progressing very rapidly and smoothly. In the upcoming two weeks traffic will be shifted to the north half of Harmony Road so that we can finish installing the concrete intersection at Ziegler Road. This second closure will be for about 2 weeks. Traffic will be set back to normal with traffic on both sides of the median on August 20, 2007. After August 20, there will still be a substantial amount of work to do. This work can be done with single lane closures on the north and south sides of Harmony Road. There will also be substantial work along Ziegler Road that will be done in lane closures. Stay posted to this website for more details.

We greatly appreciate the cooperation that has been shown by neighboring businesses and the general public. We have had a few residents and businesses contact us with specific requests and we have tried to resolve those issues. We are always happy to answer any questions or listen to any comments that you may have. Thanks for all of your cooperation and patience.

Please feel free to contact me with any questions or concerns:

Mark Laken – Project Engineer
Phone: 970-222-3546
Email:

Project Links
construction image

Northstar Concrete installs curb using a Gomaco slip-form curb machine that uses sensors that run along the stringline to place the curb and gutter.

construction image

Asphalt being milled and Traffic signals removed at Ziegler-Harmony Intersection.

construction image

Schmidt Earth prepares the ground for the concrete pavement.

construction image

Northstar Concrete pours concrete pavement in the early morning hours.