Project Closeout#

All tasks in citizen access need to be completed to closeout a project:

Uncompleted permits will expire. Expired permits become an open violation on the property. 

Completed projects will show a "completed" status in citizen access.

Some projects will receive a completion document which can be downloaded from Citizen Access (under the attachments tab)

  • Letter of Completion (LOC):
    • Shell only buildings intended for occupancy at a later time
    • Remodels
  • Certificate or Occupancy (CO):
    • New buildings to be occupied
    • First time tenant in an empty core and shell building
    • Change of use or occupancy

Task in Citizen access Action Required Contact to resolve  Staff Timeline 

Bldg Dept Req Docs

Building Code Plan Review

 E-mail documents 

buildingdocs@fcgov.com

24-48 hrs

(on business days)

Building Insp Completed

Building Inspections

Schedule and pass all Inspections

Scheduling options and contact info: 

Building Inspections

(same-day inspections are not offered, schedule the day before). 

 

Cust Svc Meter Verif

Electric Meters

Schedule Inspection 

Inspections: 970‐224‐6093

Meter Shop: 970‐221‐6382

 
Engineering Final  Schedule Inspection  970‐221‐6609  
Environmental Compliance
  • Complete online Construction Waste Management Report.
  • Upload all waste and recycling documents.

 

environmentalcompliance@fcgov.com 

48 hrs

Fire Authority Final

Poudre Fire Authority

Schedule Inspection online

Schedule Inspection 48 hrs

NonCity WWW Final

(non city water service districts)

E-mail and request sign-off after both of the following building inspections have been passed:

  • water line inspection
  • sewer line inspection

 

Buildingservices@fcgov.com 24hrs 

Water Utilities Engineering

Site Grading 

E-mail documents

  • Overall site drainage certification from the registered professional engineer certifying compliance with the approved plans.

WaterUtilitiesEng@fcgov.com 

970-224-6191

2 weeks

SW Erosion Final 

Stormwater Utilities Erosion 

Follow instructions in citizen access erosion@fcgov.com   
SW Flood Plain Final 

E-mail documents

  • New buildings and additions located in floodplains: Send FEMA elevation certificate by surveyor 
floodplains@fcgov.com 2-3 weeks

Soil Prep Certification

Soil amendments 

E-mail documents

  • Certification and proof of work
  • Inspection may be required after staff review of documents
erosion@fcgov.com  2 weeks
WWW Gen Backflow Final 

E-mail documents

  • Backflow test report 
  • Inspection may be required

nmill@fcgov.com 

970-416-2249

24 hrs

WWW Irrigation Final 

Utilities Irrigation

E-mail documents

  • Irrigation plans
eolson@fcgov.com  1 week

Water Meter Final 

(Fort Collins Water District)

Schedule Inspection WaterMeterAdmin@fcgov.com  
Zoning Final 

E-mail documents

  • New Residential Buildings:
    • Improvement Location Certificate (ILC) 
    • Street Tree permit from Forestry Department (or escrow)

Inspection

  • Commercial and Multi-family:
    • Site and Landscape inspection or escrow 

 

zoning@fcgov.com

970-416-2745

1 week