2020 Year In Review#
State Permitting Began#
The City of Fort Collins must pursue two state permitting processes in order to obtain a federal permit from the U.S. Army Corps of Engineers (Corps) to enlarge Halligan Reservoir. These two processes began in 2020.
Fish and Wildlife Mitigation and Enhancement Plan (FWMEP)
Under Colorado law, fish and wildlife resources impacted by water development projects, such as the Halligan Water Supply Project, must be mitigated. To ensure that any impacts to fish and wildlife are mitigated, the City must develop a FWMEP that will be reviewed by both the Colorado Parks and Wildlife (CPW) Commission and the Colorado Water Conservation Board (CWCB). The process is expected to take one to two years.
Get Involved
The CPW Commission and CWCB meetings are open to the public and interested organizations or individuals will be able to review the FWMEP and comment at the meetings. The FWMEP is anticipated sometime in 2022.
401 Water Quality Certification
Under Section 401 of the Clean Water Act (CWA), a federal agency may not issue a permit or license to conduct any activity that may result in any discharge into waters of the United States unless a Section 401 water quality certification is issued by the state. The City of Fort Collins will submit a 401 Certification application to the Water Quality Control Division of the Colorado Department of Public Health and Environment. The state has one year to review the application and grant, grant with conditions, or deny the Certification. The 401 Certification verifies compliance with water quality requirements. It is anticipated to take three to four years to develop a 401 Certification application.
Get Involved
The application will be available for public review and comment.
Our ongoing water quality sampling and analyses for the project were augmented to support the 401 certification application.
Environmental Impact Statement (EIS)#
The Corps issued a draft EIS and Conceptual Mitigation Plan in November 2019 and a public hearing was held in Fort Collins in January 2020.
Approximately 80 people attended the hearing. The Corps received approximately 60 written and oral comments on the draft EIS.
Together, with the Corps, we evaluated each comment on the EIS or Conceptual Mitigation Plan to determine how to address each comment. The Corps is currently developing the final EIS and the City is developing the Final Conceptual Mitigation Plan to be issued concurrently. Throughout 2020 the EIS and associated documents have been updated to address those comments.
A digital animation was created to better communicate what we heard from the comments and how they’re being addressed.
Get Involved
The final EIS is expected to be released in 2021 or 2022. It will be available for public review and comment.
Preliminary Design#
The design engineer and construction contractor were hired in mid-2020. Utilities is using a method of early contractor involvement where the contractor who will build the project is part of the design from the beginning.
A field investigation was conducted, including collecting site information to determine the integrity of the existing dam, along with the soil, bedrock and groundwater conditions around the location of the enlarged dam. The investigation also included an evaluation of on-site materials that may be used during construction.
Preliminary design began, which includes developing a conceptual layout of the new dam and spillway.
Crews drill for core samples at Halligan Reservoir
Crews scale Halligan Dam to extract cores
Crews scale Halligan Dam to extract cores
Looking Forward
Preliminary design information will be used to update the cost estimate for the project in 2022.
Outreach and Communications#
Since January 2019, there have been approximately 285,000 customer 'touchpoints' via website visits, ads, video views, stakeholder communications, newsletters, bill inserts, social media, events, and presentations.
Right of Way Acquisition#
Fort Collins Utilities is working with landowners to acquire easements for three phases of the project:
- Permitting and design
- Construction
- Operations and maintenance
Work during 2020 focused on the acquisition of easements for phase 1.
Stream Gage Installation#
Fort Collins Utilities partnered with the United States Geological Survey (USGS) and CPW to install a new stream gage upstream of Halligan Reservoir on the North Fork of the Poudre. The stream gage was funded by the City and a grant from the USGS. The gage will be maintained by the USGS and funded by the City. The gage provides useful streamflow data for design and will inform future operations of an enlarged Halligan Reservoir.
Ecological Resources#
Baseline ecological resource monitoring was conducted to obtain more detail about areas that may be impacted by the project and inform mitigation planning.
Project Schedule#
This schedule reflects the current understanding of project timelines and is subject to change based on permitting requirements. The faded bars indicate uncertainty in the schedule and capture a range of scenarios that could impact the overall schedule. The project schedule is driven predominantly by the permitting processes and staff have limited control over those processes and schedules. Given the long-term nature of the project and the permitting steps remaining, the schedule will continue to be presented as a range of timeframes.
Cost#
Based on current information, the project costs could vary between $100 million to $150 million. Information gained from preliminary design, the FWMEP and water quality analyses will be used to update the cost estimate for the project in 2022. Costs are anticipated to change and likely grow as permitting requirements and design are better understood.